Norham Gardens
Oxford University
CLIENT

LOCATION
Oxford University
Scope of work
TMP Interiors was entrusted to deliver interior works in a café area within an operational Oxford University site. This project required precision and adaptability to meet both the architectural vision and the client's high standards.
Despite the challenges, TMP Interiors collaborated closely with Kingerlee to overcome manufacturing and logistical hurdles. The team’s problem-solving approach ensured a high-quality end product, enhancing the café area’s aesthetic and functional appeal while adhering to the project timeline.
This project underscores TMP Interiors’ ability to manage unforeseen challenges and deliver superior results under tight schedules, demonstrating the value of long-standing client relationships.



Project Highlights
Hunter Douglas Ceiling
-
Supplied and installed a premium wood ceiling system.
-
Integrated a perimeter sloping transition for seamless aesthetic flow.
-
Executed during the operational shutdown period over the summer holiday.
Interior Upgrades
-
Upgraded internal door sets and glazed screens to enhance functionality and aesthetics.
Challenges
Manufacturing Issues
-
Delays and discrepancies in the supply of door sets and glazed screens led to programme disruptions.
-
Additional on-site remedial works and adjustments were necessary to address quality concerns.
Reactive Procurement
-
Last-minute procurement efforts were undertaken to source and install compliant materials, ensuring the project met the client’s exacting standards.